CONSTRUCTION OF RIVER TRAINING WORKS AT RIVER INDUS
SIR AGA KHAN JHIRK MULLAH KATIYAR BRIDGE
The main bridge on river indus has been completed along with the approach roads. The project has been opened for traffic in February 2017. However, the river training works could not be started due to various reasons and court order. Almost 70 percent of the river training works which includes Construction of Guide Bank, Construction of Apron and Spur has been completed and while 30 percent work is still remaining which has been held up for want of clearance of High Court of Sindh and subsequent handing over of land for starting the work. Total cost of River Training Works is 558 Millions
PROJECT SCOPE
CONSTRUCTION OF MAIN BRIDGE STRUCTURE
Heavy Excavation for Apron Dumping of Heavy Stones for Apron
Preparation of Embankment for Guide Bank Stone Pitching on Guide Bank
Stone Toe Wall for Guide Bank Service Road on Top of Guide Bank