Construction of Flyover at University Road Intersection

Client: Works & services Group of Offices, CDGK.
Amount of work: Rs.246,899,698
Revised Amount Rs.304,660,698
Location Karachi
Year at start March, 2009
Year of Completion: July, 2009

Project Background:

There had been lot of traffic jams on university road at the intersection of road leading to johar chorangi, about 50% vehicles from NIPA Chorangi diverted toward johar chowrangi for reaching their destination in Gulistan-e-jouhar beyond to airport. The City Distt govt Karachi with the assistance of Govt of Sindh started the work on corridor iv to make university road as signal free corridor from sadder to safora goth. After completion of this flyover in record time of 5 month all the traffic congestion had been removed.

Project Scope
Erecting of piles & pile Caps
Construction of Pier Shafts
Construction of Transforms
Construction of Girders
Construction of Deck Slabs
Construction of Retaining Walls and Ramps
Erecting of Electric Poles & Lights