IMPROVEMENT OF MAIN HAWKSBAY ROAD 5TH AVENUE TO T-JUNCTION

Client: Works & services Group of Offices, CDGK.
Amount of work: Rs. 557,129,089
Revised amount
Location Karachi
Year at start July, 2012
Project status: Work in progress

Project Background:

The existing main hawksbay road is in dilapidated condition the width of existing track is only 24ft which are not sufficient for increasing traffic resulting existing drainage system is not proper so the area remain inundated under rainwater. Necessary drainage has been proposed for new works and widening of existing track from 24ft to 48 ft. A new service road of 24ft width will be constructed.

 

Project Scope
Construction of Culverts
Construction of RCC storm Water Drain
Preparation of Embankement
Construction of Road
Carpeting of Road
Laying of pipe for pipe drain