Client:
|
Works & services Group of Offices, CDGK. |
| Amount of work: | Rs.173,958,076 |
| Location | Karachi |
| Year at start | Feb,2009 |
| Year of Completion: | June,2009 |
| Actual year of Completion | October, 2009 |
Project Background:
This project is a part of corridor iv of university Road to make it signal free from sadder to safora Chowk / Malir Cantt. Most of the peoples residing near Isphani road, sohrab goth, block 7 of Gulshan-e-iqbal & Metro normally use Isphahani road. There had been lot of traffic Jams & accident over here. After completion of this flyover the motorist have got relief resulting in saving of time, fuel & money.
| Project Scope |
|---|
| Erecting of piles & pile Caps |
| Construction of Pier Shafts |
| Construction of Transforms |
| Construction of Girders |
| Construction of Deck Slabs |
| Construction of Retaining Walls and Ramps |
| Erecting of Electric Poles & Lights |